Record Transformer Repair Restores 200 MW Power in Just 26 Days in Iran

In a remarkable feat, Iran's Power Plant Repair Company successfully repaired a 200 MVA transformer at the Shahid Soleimani power plant in Kerman within 26 days, a process that typically takes 120 days.

The rapid response team undertook a comprehensive operation involving:

  • Disassembly and relocation of the damaged transformer.

  • Reconstruction of the high-voltage coil.

  • Replacement and reassembly of the transformer.

  • Specialized testing for low and high voltage.

This swift action restored 200 MW of electricity to the national grid, alleviating production constraints from associated gas and steam units.

The success is attributed to the expertise and dedication of the team, operating three shifts without interruption, showcasing a significant advancement in Iran's power engineering capabilities.